New HQ Publication

November 2021

Marigold Library System and the Western Irrigation District moved into the new facility. A Grand Opening ceremony will take place in 2022.

devon2.png

April 2021

Roofing and steel studs are nearing completion. Concrete pads are being polished and windows are being framed. Cabling and electrical are underway.

IMGL5466-Online.png

November 2020

The Marigold Library System and Western Irrigation District new Headquarters' groundbreaking ceremony officially kicked off the construction process.

group shot-online.png

April 2020

Shovels are expected to be hitting the ground by June. Marigold staff are meeting with the Town of Strathmore regarding Development and Building permits.

IMGL0755 (1).jpg

November 2019

Marigold Library System and the Western Irrigation District met to discuss cost savings and core needs of both organizations.

Marigold-stock.jpg

August 2021

The facility has undergone significant changes and the Marigold Library System and Western Irrigation District staff are eagerly awaiting their move into the new building. 

IMGL6359-Online.png

January 2021

Steel installation is complete, the structure is enclosed and tented and the pouring of the interior concrete pads has begun. 

IMGL4202-SW corner - online.png

August 2020

Western Irrigation District excavators began site clearing to level and prepare the site. The Building Permit was approved and signed.

IMGL0702-print.jpg

January 2020

The joint facility project is inching closer to construction with the Development and Design phase completed.

cover new HQ.png

August 2019

Meetings take place with architects and between Marigold Library System and the Western Irrigation System. Marigold staff get to see building plans.