Here's what's happening this month:

  • Telecommunications and fibre installations are being coordinated with various vendors.

  • The Western Irrigation District crew is completing more site prep as Lear will be working on sidewalks and pavement in the following weeks, in addition to pouring ramps, aprons and entryway slabs.

  • Drywall in the Marigold wing is nearly complete and the large common area multipurpose spaces are underway.

  • Painting has started in the Marigold wing open office area, which will be followed by the installation of the raised access flooring.

  • The WID overhead shop doors are installed with motors and power to follow. Audiovisual and security system electrical work is underway with our electrical engineer from WSP.